Work 1
In progress25%Physical progress
24.8%Financial progress
Scheduled start02-06-2025
Scheduled completion02-03-2026
- Contractor
- Abishekbaby
- Implementing agency (SPV)
- KIIDC
- Contract amount
- ₹5,86,81,195₹5.87 crore
- Amount paid
- ₹1,45,72,148₹1.46 crore
- Paid to contractor
- ₹1,37,69,444₹1.38 crore
- Administrative sanction (AS)
- ₹13,50,00,000₹13.5 crore
- Financial sanction (FS)
- ₹5,37,00,000₹5.37 crore
- Technical sanction (TS)
- ₹5,33,57,991₹5.34 crore
- Tender amount
- ₹5,86,81,195₹5.87 crore