Kanakkuമലയാളം
WRD025-18-02 Kongad

2017-18-CWSS to Karimba, kongad and Mundur(part) Panchayaths- Phase I- Package II- 1300LL OHSR,450mm CWPM,200mm CWGM.

Spent on this package so far

₹1.28 crore

₹1,28,22,777

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹28,30,27,826Estimate of sub-project WRD025-18, shared by 3 contract packages
Expenditure reported · this package
₹1,28,22,777
Expenditure reported · all 3 packages
₹10,02,85,52135.4% of the estimated amount

Details

Project code
WRD025-18-02
Department
Water Resources
Constituency
KongadMLA: Smt. Santhakumari. K
Name as KIIFB publishes it
KIIFB-2017-18-CWSS to Karimba, kongad and Mundur(part) Panchayaths- Phase I- Package II- 1300LL OHSR,450mm CWPM,200mm CWGM.

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Comprehensive Drinking Water projects - Karimba and Kongad Panchayaths in Palakkad District”. The figures below are for that whole project, not this package alone.

Approved
₹28,30,27,826₹28.3 crore
Paid so far
₹10,99,44,07338.8% of the amount approved

This package

Work awarded
₹1.41 crorepaid
₹13.91 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project