WRD025-27-03 Kanjirappally

2017-2018 – Wrd – 025 – 27 – Karimpukayam Water Supply Project - Augumentation of Arwss to Kanjirappally, Elikkulam and Chirakkadavu Panchayaths in Kottayam District - Package – II – 1) 300mm Dia DI K9 Pumping Main from Cw Sump at Gramadeepam to Glsr at Thambalakkadu, 2 ) 250 Mm DI K9 Clear Water Pumping Main from Sump at Gramadeepam to OHSR at Ponkunnam, 3) Distribution Network in Chirakkadavu Pt. - Zone 1B, Zone 4 and ZONE5 4) Road Restoration.

Spent on this package so far

₹8.57 crore

₹8,57,11,493

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹68,64,28,000Estimate of sub-project WRD025-26, shared by 3 contract packages
Expenditure reported · this package
₹8,57,11,493
Expenditure reported · all 3 packages
₹8,57,11,49312.5% of the estimated amount

Details

Project code
WRD025-27-03
Department
Water Resources
Constituency
KanjirappallyMLA: DR. N. Jayaraj
Name as KIIFB publishes it
KIIFB – 2017-2018 – WRD – 025 – 27 – KARIMPUKAYAM WATER SUPPLY PROJECT - AUGUMENTATION OF ARWSS TO KANJIRAPPALLY, ELIKKULAM AND CHIRAKKADAVU PANCHAYATHS IN KOTTAYAM DISTRICT - PACKAGE – II – 1) 300mm Dia DI K9 PUMPING MAIN FROM CW SUMP AT GRAMADEEPAM TO GLSR AT THAMBALAKKADU, 2 ) 250 MM DI K9 CLEAR WATER PUMPING MAIN FROM SUMP AT GRAMADEEPAM TO OHSR AT PONKUNNAM, 3) DISTRIBUTION NETWORK IN CHIRAKKADAVU PT. - ZONE 1B, ZONE 4 AND ZONE5 4) ROAD RESTORATION.

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Karimpukayam Water Supply Project - Augmentation of ARWSS to Kanjirappally, Elikkulam and Chirakkadavu Panchayaths in Kottayam District”. The figures below are for that whole project, not this package alone.

Approved
₹68,64,28,000₹68.64 crore
Paid so far
₹10,28,82,58515% of the amount approved

This package

Work awarded
₹9.36 crorepaid
₹23.88 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026