WRD025-33-01 Chittur

Comprehensive Drinking Water Schemes To Perumatty,Pattenchery,Elappully and Nallepilly Panchayaths in Palakkad District-Phase II – Package I - Construction of OHSRs, Laying CWPMs including Road restoration

Spent on this package so far

₹12.2 crore

₹12,20,39,492

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: Contract Process Completed · How we group

Location

Money trail

Estimated amount
₹29,10,00,000Estimate of sub-project WRD025-33, shared by 2 contract packages
Expenditure reported · this package
₹12,20,39,492
Expenditure reported · all 2 packages
₹20,77,71,80671.4% of the estimated amount

Details

Project code
WRD025-33-01
Department
Water Resources
Constituency
ChitturMLA: Shri K. Krishnankutty

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Comprehensive Drinking Water Schemes to Perumatty,pattenchery,elappully,nallepilly Panchayaths in Palakkad District-Phase II”. The figures below are for that whole project, not this package alone.

Approved
₹29,10,00,000₹29.1 crore
Paid so far
₹22,83,30,88778.5% of the amount approved

This package

Work started
₹13.53 crorepaid
₹14.28 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project