Named on 0 works on the KIIFB dashboard and 8 works on PWD's liability list.

Value of KIIFB contracts

Not published

No contract amount on the KIIFB dashboard.

Recorded as paid by KIIFB

Not published

PWD works under liability now

8

We treat different spellings of a name as one contractor. Two different contractors with the same name may therefore appear as one; the sources give contractors no identifier.

Works on PWD's liability list (8)

  1. Annual Plan 2019-20 Construction of School Building of Government LP School Palvelicham , WayanadBuildings · Buildings Sub Division PunalurSajeev MathaiLiable from 29-03-2022 until 29-03-2027
  2. MLA-ADS-2019-20-Pattanapuram LAC, Construction of new building for Govt. Homeo Dispensary Pattazhy Vadakkekara .Buildings · Buildings Sub Division PunalurSajeev MathaiLiable from 29-03-2022 until 29-03-2027
  3. LAC-ADS-MLA-ADS-2019-20-Pattanapuram LAC, Construction of new building for Govt. Homeo Dispensary Pattazhy Vadakkekara .-Work-General Civil Work-1Buildings · Buildings Sub Division PunalurSajeev MathaiLiable from 29-03-2022 until 29-03-2027
  4. CONSTRUCTION OF NEW BUILDING FOR GOVT MUSLIM UPS, EDAVA, VARKALA-PHASE 1Buildings · Buildings Sub Division AttingalSajeev MathaiLiable from 14-03-2022 until 14-03-2028
  5. Construction of New building for Govt. UPS Manchavilakam.Buildings · Buildings Sub Division AttingalSajeev MathaiLiable from 14-03-2022 until 14-03-2028
  6. LAC-ADS-MLA-ADS 2019-20 & 2020-21 Sri.K.B.Ganeshkumar MLA, Pathanapuram LAC: Construction of a New Building for Police Control Room at Pathanapuram Phase-I&II-Work-General Civil Work-1Buildings · Buildings Sub Division PunalurSajeev MathaiLiable from 04-05-2023 until 04-05-2028
  7. MLA- ADS- 2019 -20 Nemom Constituency '( PHASE 3) - Construction of First Floor and Stair Room for Govt. Ayurveda Hospital at Nemom, ThiruvananthapuramBuildings · Buildings Sub Division NeyyanttinkaraSajeev MathaiLiable from 17-05-2023 until 17-05-2028
  8. MLA-ADS-2020-21 Nemom Constituency (PHASE 4) - Balance work for the construction of First Floor and Stair Room for Govt. Ayurveda Hospital at Nemom , ThiruvananthapuramBuildings · Buildings Sub Division NeyyanttinkaraSajeev MathaiLiable from 24-05-2023 until 24-05-2028