Kanakkuമലയാളം
PowerApproved

GAS INSULATED SUBSTATION PACKAGE-IV Thalassery and Thuravoor

Approved by KIIFB

₹65.41 crore

₹65,41,32,403

Paid so far

₹58.42 crore

₹58,41,81,140 · 89.3% of the amount approved

Works

1

₹58.42 crore paid across the works

Works (1)

Details

Department
Power
Implementing agency (SPV)
KSEBL Transgrid
Announced under
Transgrid Project KSEB
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
02-10-2026
First recorded
30-09-2026

The same project on the map dashboard

KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.