This package
Work awarded₹58.42 crorepaid
₹60.37 croreapproved
₹65.41 crore
₹65,41,32,403 · ₹57.06 crore spent
KIIFB status: WBS Base One Approved · How we group
On KIIFB's project status page this belongs to “GAS INSULATED SUBSTATION PACKAGE-IV Thalassery and Thuravoor”.
Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources
The KIIFB dashboard does not publish these for this project: