Thrissur Cluster Phase 2

Approved by KIIFB

₹39.49 crore

₹39,48,52,000

Paid so far

₹31.44 crore

₹31,43,54,681 · 79.6% of the amount approved

Works

12

₹31.44 crore paid across the works

KIIFB's list gives “payment released” for this project as ₹2,51,48,37,448. That is exactly 8 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹31,43,54,681.

Works (12)

Total of the works: ₹36,70,79,522 approved, ₹31,43,54,681 paid.

Details

Department
General Education
Announced under
PPE Mission-Upgradation of one school in each constituency
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
02-10-2026
First recorded
30-09-2026

The same project on the map dashboard

KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.