GED005-18-11 Kaipamangalam

GKVHSS Eriyad - Cluster 13A

Spent on this package so far

₹5.73 crore

₹5,73,05,797

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹39,48,52,000Estimate of sub-project GED005-18, shared by 12 contract packages
Expenditure reported · this package
₹5,73,05,797
Expenditure reported · all 12 packages
₹29,78,88,62875.4% of the estimated amount

Details

Project code
GED005-18-11
Department
General Education
Constituency
KaipamangalamMLA: Shri E. T. Taison Master

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Thrissur Cluster Phase 2”. The figures below are for that whole project, not this package alone.

Approved
₹39,48,52,000₹39.49 crore
Paid so far
₹2,51,48,37,448₹251.48 crore

Source: KIIFB project status (kiifb.org). How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress