Kannur Cluster - 17
Approved by KIIFB
₹14.44 crore
₹14,44,09,086
Paid so far
₹13.99 crore
₹13,98,83,459 · 96.9% of the amount approved
Works
15
₹13.99 crore paid across the works
KIIFB's list gives “payment released” for this project as ₹69,94,17,295. That is exactly 5 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹13,98,83,459.
Works (15)
₹87.99 lakhpaid
₹89.28 lakhapproved
GHSS Ulikkal
Work awarded₹99.31 lakhpaid
₹99.52 lakhapproved
GWHSS Cherukunnu
Work awarded₹81.59 lakhpaid
₹89.71 lakhapproved
GHS Padiyoor
Work started₹97.24 lakhpaid
₹1 croreapproved
GHSS Mambaram
Work awarded₹88.36 lakhpaid
₹88.39 lakhapproved
GHSS Prapoyil
Work awarded₹1.14 crorepaid
₹1.15 croreapproved
GHSS Kozhichal
Work awarded₹97.99 lakhpaid
₹98.67 lakhapproved
GHSS Peringome
Work awarded₹1.01 crorepaid
₹1.02 croreapproved
GHSS Chattukappara
Work awarded₹97.48 lakhpaid
₹97.55 lakhapproved
GBVHSS Madayi
Work awarded₹87.64 lakhpaid
₹88.01 lakhapproved
Project Improvement of Infrastructure Facilities to GHSS Kadannappalli under Kalliassery LAC in Kannur District Panchayath
Work awarded₹99.15 lakhpaid
₹1 croreapproved
Project Improvement of Infrastructure Facilities to GHS Rayarome under Irikkur LAC in Kannur District Panchayath
Work awarded₹80.07 lakhpaid
₹83.58 lakhapproved
Project Improvement of Infrastructure Facilities to GHS Thadikkadavu under Thalipparamba LAC in Kannur District Panchayath
Work awarded₹83.73 lakhpaid
₹87.53 lakhapproved
Project Improvement of Infrastructure Facilities to AKSGHS Malappatam under Thaliparamba LAC in Kannur District Panchayath
Work awarded₹83.93 lakhpaid
₹92.36 lakhapproved
Project Improvement of Infrastructure Facilities to GHS Kalikkadavu under Thaliparamba LAC in Kannur District Panchayath
Work awarded₹99.47 lakhpaid
₹99.8 lakhapproved
Total of the works: ₹14,31,75,527 approved, ₹13,98,83,459 paid.
Details
- Department
- General Education
- Implementing agency (SPV)
- Kerala Institute of Local Administration (KILA)
- Announced under
- Betterment of Infrastructure facilities in 446 schools- 1 Cr category-KILA
- KIIFB status
- Approved
Source
- Source
- KIIFB project statuskiifb.org/prjStatus.jsp
- Amounts retrieved
- 30-09-2026
- Works last checked
- 02-10-2026
- First recorded
- 30-09-2026
The same project on the map dashboard
KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.
- GHSS Prapoyil GED003-17-06 · ₹1.1 crore spent
- GHSS Peringome GED003-17-08 · ₹97.89 lakh spent
- Project Improvement of Infrastructure Facilities to GHS Kalikkadavu under Thaliparamba LAC in Kannur District Panchayath GED003-17-15 · ₹96.1 lakh spent
- GHSS Ulikkal GED003-17-02 · ₹95.82 lakh spent
- Project Improvement of Infrastructure Facilities to GHSS Kadannappalli under Kalliassery LAC in Kannur District Panchayath GED003-17-11 · ₹95.59 lakh spent
- GHSS Kozhichal GED003-17-07 · ₹94.67 lakh spent
- GHSS Chattukappara GED003-17-09 · ₹94.02 lakh spent
- GHS Padiyoor GED003-17-04 · ₹93.85 lakh spent
- GHSS Mambaram GED003-17-05 · ₹85.3 lakh spent
- GVHSS Karthikapuram GED003-17-01 · ₹84.93 lakh spent
- GBVHSS Madayi GED003-17-10 · ₹84.5 lakh spent
- Project Improvement of Infrastructure Facilities to AKSGHS Malappatam under Thaliparamba LAC in Kannur District Panchayath GED003-17-14 · ₹81.08 lakh spent
- Project Improvement of Infrastructure Facilities to GHS Thadikkadavu under Thalipparamba LAC in Kannur District Panchayath GED003-17-13 · ₹80.66 lakh spent
- GWHSS Cherukunnu GED003-17-03 · ₹78.71 lakh spent
- Project Improvement of Infrastructure Facilities to GHS Rayarome under Irikkur LAC in Kannur District Panchayath GED003-17-12 · ₹77.28 lakh spent