Kanakkuമലയാളം

Spent on this package so far

₹97.89 lakh

₹97,88,729

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹14,44,09,086Estimate of sub-project GED003-17, shared by 15 contract packages
Expenditure reported · this package
₹97,88,729
Expenditure reported · all 15 packages
₹13,50,07,84393.5% of the estimated amount

Details

Project code
GED003-17-08
Department
General Education
Constituency
PayyannurMLA: Shri T.I. Madhusoodanan

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Kannur Cluster - 17”. The figures below are for that whole project, not this package alone.

Approved
₹14,44,09,086₹14.44 crore
Paid so far
₹13,98,83,45996.9% of the amount approved

This package

Work awarded
₹1.01 crorepaid
₹1.02 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project