Water ResourcesApproved

Augmentation of CWSS to Nattika Firka Phase I

Approved by KIIFB

₹104 crore

₹1,03,99,58,849

Paid so far

₹27.08 crore

₹27,08,03,563 · 26% of the amount approved

Works

5

₹27.08 crore paid across the works

KIIFB's list gives “payment released” for this project as ₹1,08,32,14,252. That is exactly 4 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹27,08,03,563.

Works (5)

Augmentation of CWSS to Nattika Firka Phase-I ? Package I - 9m dia intake well cum pumphouse, 26MLD Water Treatment Plant , Renovation of existing WTP and existing intake well cum pumphouse, 2 nos RW and 2 nos CW Pumpsets, 500KVA Transformers (3 nos), 700mm DI RWPM - 2700m, restoration of roads and allied works

Work awarded
₹0paid
₹1approved

Its record on the map dashboard · WRD025-04-01

Augmentation of CWSS to Nattika Firka Phase I ? Package II - 900mm DI K9 Clear Water Pumping Main from Vellani WTP to Chuloor Junction 800mm, 700mm, 600mm, 500mm & 300mm DI K9 CWPM, installation of fire hydrant, restoration of roads after laying pipes and allied works

Work started
₹0paid
₹1approved

Its record on the map dashboard · WRD025-04-02

Augmentation of CWSS to Nattika Firka Phase-l-Package III -Dismantling existing pipe line and laying of 700/500/200 mm pipes at Proposed WTP compound, Utility shifting, Leak rectification and Interconnection work.-General Civil Work

Work awarded
₹0paid
₹2.09 croreapproved

Its record on the map dashboard · WRD025-04-03

Augmentation of CWSS to Nattika Firka Phase-l-Package I - Design,Construction and Commissioning of 9m dia intake well cum pumphouse,26MLDWater Treatment Plant at Vellani, Renovation of existing WTP at Vellani and existing intake well cum pump house at lllickal, Supply erection testing and commissioning of 2 nos RW and 2 nos CW Pumpsets, 500KVA Transformers [2nos),Supplying laying testing and commissioning 700mm DI RWPM - 2700m,restoration of roads after laying pipes and allied works.

Work awarded
₹4.21 crorepaid
₹45.64 croreapproved

Its record on the map dashboard · WRD025-04-04

Augmentation of CWSS to Nattika Firka Phase I ? Package II - Supplying, Laying, Testing and Commissioning 900mm DI K9 Clear Water Pumping Main from Vellani WTP to Chuloor Junction-7670m-800mm, 700mm, 600mm, 500mm & 300mm DI K9 CWPM from Chuloor to Kaipamangalam OH tank, Edathuruthi OH tank and Valappad OH tank. installation of fire hydrant, restoration of roads after laying pipes and allied works

Work awarded
₹22.87 crorepaid
₹56.26 croreapproved

Its record on the map dashboard · WRD025-04-05

Total of the works: ₹1,03,99,58,849 approved, ₹27,08,03,563 paid.

Details

Department
Water Resources
Implementing agency (SPV)
Kerala Water Authority (KWA)
Announced under
KIIFB 2017-18 water supply projects
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
02-10-2026
First recorded
30-09-2026

The same project on the map dashboard

KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.