Augmentation of CWSS to Nattika Firka Phase I – Package II - Supplying, Laying, Testing and Commissioning 900mm DI K9 Clear Water Pumping Main from Vellani WTP to Chuloor Junction-7670m-800mm, 700mm, 600mm, 500mm & 300mm DI K9 CWPM from Chuloor to Kaipamangalam OH tank, Edathuruthi OH tank and Valappad OH tank. installation of fire hydrant, restoration of roads after laying pipes and allied works
Spent on this package so far
₹11.91 crore
₹11,90,75,175
Stage
- Preparation
- Technical sanction
- Tender
- Contract
- Work plan
KIIFB status: WBS Base One Approved · How we group
Money trail
- Estimated amount
- ₹1,03,99,58,849Estimate of sub-project WRD025-04, shared by 5 contract packages
- Expenditure reported · this package
- ₹11,90,75,175
- Expenditure reported · all 5 packages
- ₹11,90,75,17511.4% of the estimated amount
Details
- Project code
- WRD025-04-05
- Department
- Water Resources
- Executing agency
- Kerala Water Authority (KWA)
- Constituency
- GuruvayoorMLA: Shri N. K. Akbar
- Constituency
- ManalurMLA: Shri Murali Perunelly
- Constituency
- NattikaMLA: Shri C.C. Mukundan
- Constituency
- KaipamangalamMLA: Shri E. T. Taison Master
What KIIFB approved and paid
On KIIFB's project status page this belongs to “Augmentation of CWSS to Nattika Firka Phase I”. The figures below are for that whole project, not this package alone.
- Approved
- ₹1,03,99,58,849₹104 crore
- Paid so far
- ₹1,08,32,14,252₹108.32 crore
Source: KIIFB project status (kiifb.org). How we joined the two sources
What we don't know yet
The KIIFB dashboard does not publish these for this project:
- Contractor, contract amount, scheduled dates, payments and physical progress
Source
- Source
- KIIFB integrated dashboardgis.kiifb.org
- Retrieved
- 30-09-2026
- First recorded
- 30-09-2026
- SHA-256
- 04a00101b9212117…
Other packages under the same sub-project
- Augmentation of CWSS to Nattika Firka Phase-I – Package I - 9m dia intake well cum pumphouse, 26MLD Water Treatment Plant , Renovation of existing WTP and existing intake well cum pumphouse, 2 nos RW and 2 nos CW Pumpsets, 500KVA Transformers (3 nos), 700mm DI RWPM - 2700m, restoration of roads and allied works Not published
- Augmentation of CWSS to Nattika Firka Phase I – Package II - 900mm DI K9 Clear Water Pumping Main from Vellani WTP to Chuloor Junction 800mm, 700mm, 600mm, 500mm & 300mm DI K9 CWPM, installation of fire hydrant, restoration of roads after laying pipes and allied works Not published
- Augmentation of CWSS to Nattika Firka Phase-l-Package III -Dismantling existing pipe line and laying of 700/500/200 mm pipes at Proposed WTP compound, Utility shifting, Leak rectification and Interconnection work.-General Civil Work Not published
- Augmentation of CWSS to Nattika Firka Phase-l-Package I - Design,Construction and Commissioning of 9m dia intake well cum pumphouse,26MLDWater Treatment Plant at Vellani, Renovation of existing WTP at Vellani and existing intake well cum pump house at lllickal, Supply erection testing and commissioning of 2 nos RW and 2 nos CW Pumpsets, 500KVA Transformers [2nos),Supplying laying testing and commissioning 700mm DI RWPM - 2700m,restoration of roads after laying pipes and allied works. Not published