Kanakkuമലയാളം
Water ResourcesApproved

WSS to Ramanchady - Aligar in Malappuram District

Approved by KIIFB

₹92.52 crore

₹92,52,32,458

Paid so far

₹63.62 crore

₹63,62,45,855 · 68.8% of the amount approved

Works

11

₹63.62 crore paid across the works

Works (11)

WSS to Ramanchady-Aligar in Malappuram District - Land Purchase - Package - IV

Work awarded
₹0paid
₹10 lakhapproved

Govt Payment - KIIFB 2017-18 - WSS to Ramanchady-Aligar in Malappuram District - Power line extension - Stage - I - Package - I (A)

Work awarded
₹0paid
₹48.7 lakhapproved

License Fee Payable to NHAI for Road Restoration of NH-966 in Perinthalmanna Town

Work awarded
₹0paid
₹97.51 lakhapproved

WSS to Ramanchadi-Aligrah in Malappuram District -Package - III (B) - Supplying, Laying, Testing and Commissioning 400 Mm & 250 Mm DI K9 Pipes-Pipeline Work

Work awarded
₹2.56 crorepaid
₹2.72 croreapproved

Its record on the map dashboard · WRD025-13-06

WSS to Ramanchady - Aligar in Malappuram District- Road Restoration Charges to KSTP

Work awarded
₹2.98 lakhpaid
₹2.98 lakhapproved

WSS to Ramanchady - Aligar in Malappuram District- KSEB Feeder line extension to Pump house, Booster station and WTP

Work awarded
₹6.2 crorepaid
₹6.24 croreapproved

Payment toward Electrical inspectorate for the inspection of transformer and allied components

Work awarded
₹37,730paid
₹37,730approved

WSS To Ramanchadi Aligrah in Malappuram DT - Payment toward Electrical inspectorate for Last defects of all three sites

Work awarded
₹0paid
₹96,045approved

Total of the works: ₹77,37,02,323 approved, ₹63,62,45,855 paid.

Details

Department
Water Resources
Implementing agency (SPV)
Kerala Water Authority (KWA)
Announced under
KIIFB 2017-18 water supply projects
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
02-10-2026
First recorded
30-09-2026

The same project on the map dashboard

KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.