WRD025-13-02 Perinthalmanna

Budget 2017 -18 - WSS to Ramanchadi - Aligarh in Malappuram District - Package - II - Laying Distribution Main

Spent on this package so far

₹18.98 crore

₹18,97,94,178

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹92,52,32,458Estimate of sub-project WRD025-11, shared by 6 contract packages
Expenditure reported · this package
₹18,97,94,178
Expenditure reported · all 6 packages
₹56,27,46,31360.8% of the estimated amount

Details

Project code
WRD025-13-02
Department
Water Resources
Constituency
PerinthalmannaMLA: Shri Najeeb Kanthapuram
Name as KIIFB publishes it
KIIFB - Budget 2017 -18 - WSS to RAMANCHADI - ALIGARH IN MALAPPURAM DISTRICT - PACKAGE - II - LAYING DISTRIBUTION MAIN

What KIIFB approved and paid

On KIIFB's project status page this belongs to “WSS to Ramanchady - Aligar in Malappuram District”. The figures below are for that whole project, not this package alone.

Approved
₹92,52,32,458₹92.52 crore
Paid so far
₹63,62,45,85568.8% of the amount approved

This package

Work awarded
₹19.67 crorepaid
₹23.83 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project