Construction of Zilla Court Bridge across in Alappuzha District
Approved by KIIFB
₹120.52 crore
₹1,20,52,00,000
Paid so far
₹62.87 crore
₹62,86,91,923 · 52.2% of the amount approved
Works
5
₹62.87 crore paid across the works
KIIFB's figures do not agree here: its list says ₹1,20,52,00,000 was approved for the project, while the approvals of the works add up to ₹1,28,24,72,765. Both are shown as the source states them.
Works (5)
Zilla Court Bridge across in Alappuzha District-LA
Work awarded
₹20.58 crorepaid
₹22.5 croreapproved
Construction of Zilla Court Bridge across in Alappuzha District - Contract