Zilla court bridge
In progress14.8%Physical progress
19%Financial progress
Scheduled start31-08-2024
Scheduled completion30-08-2026
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹1,01,06,27,813₹101.06 crore
- Amount paid
- ₹19,25,07,153₹19.25 crore
- Paid to contractor
- ₹18,02,71,507₹18.03 crore
- Administrative sanction (AS)
- ₹20,00,00,000₹20 crore
- Financial sanction (FS)
- ₹1,20,52,00,000₹120.52 crore
- Technical sanction (TS)
- ₹91,89,12,291₹91.89 crore
- Tender amount
- ₹1,01,06,27,813₹101.06 crore
- Current progress
- Technical sanction estimate submitted to TL on 08.04.22.TS committee conducted on 24/05/22.Joint inspection with KSEB KWA ,BSNL conducted and Estimate received from KSEB on 29.7.2022. 19(!) declaration on 8.7.22