Kanakkuമലയാളം
Public WorksApproved

Improvements to the Hill highway road From Chevar to Edaparamba km 49.635 in Kasargode District

Approved by KIIFB

₹86.64 crore

₹86,63,89,837

Paid so far

₹74.41 crore

₹74,41,33,755 · 85.9% of the amount approved

Works

3

₹74.41 crore paid across the works

KIIFB's list gives “payment released” for this project as ₹2,23,24,01,265. That is exactly 3 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹74,41,33,755.

Works (3)

Improvements to the Hill highway road From Chevar to Edaparamba km 49.635 in Kasargode District - KWA

Work awarded
₹1.67 crorepaid
₹1.67 croreapproved

Improvements to the Hill highway road From Chevar to Edaparamba km 49.635 in Kasargode District - KSEB

Work awarded
₹1.49 crorepaid
₹1.49 croreapproved

Total of the works: ₹86,12,22,364 approved, ₹74,41,33,755 paid.

Details

Department
Public Works
Implementing agency (SPV)
Kerala Road Fund Board (KRFB)
Announced under
Hill Highway
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
02-10-2026
First recorded
30-09-2026

The same project on the map dashboard

KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.