Chevar - Edaparamba Road
In progress87.6%Physical progress
83.5%Financial progress
Scheduled start19-09-2022
Scheduled completion31-12-2025
- Contractor
- T. A. Abdul Rahiman
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹82,96,19,995₹82.96 crore
- Amount paid
- ₹69,25,21,849₹69.25 crore
- Paid to contractor
- ₹65,43,74,403₹65.44 crore
- Administrative sanction (AS)
- ₹35,00,00,00,000₹3,500 crore
- Financial sanction (FS)
- ₹86,63,89,837₹86.64 crore
- Technical sanction (TS)
- ₹83,38,08,055₹83.38 crore
- Tender amount
- ₹79,23,40,648₹79.23 crore
- Letter of acceptance (LOA)
- ₹70,74,47,007₹70.74 crore
- Current progress
- Placed in TAC on 10.06.2022