Improvements to Manackakadavu Kizhakkambalam Pattimattom
Approved by KIIFB
₹32.63 crore
₹32,63,00,000
Paid so far
₹27.98 crore
₹27,98,21,468 · 85.8% of the amount approved
Works
4
₹27.98 crore paid across the works
KIIFB's figures do not agree here: its list says ₹32,63,00,000 was approved for the project, while the approvals of the works add up to ₹33,56,46,170. Both are shown as the source states them.
Works (4)
Manackakadavu Kizhakkambalam Pattimattom - Utility shifting by KSEB
Work awarded
₹14.29 lakhpaid
₹14.29 lakhapproved
Manackakadavu Kizhakkambalam Pattimattom - Utility shifting by KWA
Work awarded
₹5.97 crorepaid
₹5.97 croreapproved
Manackakadavu Kizhakkambalam Pattimattom- Contract work