PWD004-114-04 Kunnathunad

Improvements to Manackakadavu Kizhakkambalam Pattimattom Nellad - Balance Work

Spent on this package so far

₹10.56 crore

₹10,56,42,429

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: Contract Process Completed · How we group

Location

Works (1)

Manakkakadavu- Pattimattom road

Completed
100%Physical progress
89.7%Financial progress
Scheduled start18-07-2024
Scheduled completion18-04-2025
Implementing agency (SPV)
KRFB
Contract amount
₹11,49,78,701₹11.5 crore
Amount paid
₹10,31,43,569₹10.31 crore
Paid to contractor
₹9,65,87,829₹9.66 crore
Administrative sanction (AS)
₹20,00,00,000₹20 crore
Financial sanction (FS)
₹32,63,00,000₹32.63 crore
Technical sanction (TS)
₹10,45,30,000₹10.45 crore
Tender amount
₹11,49,78,701₹11.5 crore
Current progress
This work is now under the charge of EE, PWD Roads Division Muvattupuzha.

Money trail

Estimated amount
₹32,63,00,000Estimate of sub-project PWD004-112, shared by 2 contract packages
Expenditure reported · this package
₹10,56,42,429
Expenditure reported · all 2 packages
₹20,86,26,99863.9% of the estimated amount

Details

Project code
PWD004-114-04
Department
Public Works
Constituency
Kunnathunad

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Improvements to Manackakadavu Kizhakkambalam Pattimattom”. The figures below are for that whole project, not this package alone.

Approved
₹32,63,00,000₹32.63 crore
Paid so far
₹27,98,21,46885.8% of the amount approved

This package

Work awarded
₹11.14 crorepaid
₹11.43 croreapproved

Source: KIIFB project status (kiifb.org). Checked 30-09-2026. How we joined the two sources

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project