Improvements to Amaravila - Ottasekharamangalam road by providing 50mm DBM & 30mm BC between Km 0/000 to 12/200- Package 1
Work started₹26.55 lakhpaid
₹26.55 lakhapproved
₹35.82 crore
₹35,81,50,861
₹34.7 crore
₹34,70,47,248 · 96.9% of the amount approved
5
₹34.7 crore paid across the works
KIIFB's list gives “payment released” for this project as ₹69,40,94,496. That is exactly 2 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹34,70,47,248.
Total of the works: ₹35,81,44,362 approved, ₹34,70,47,248 paid.
KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.
| Retrieved | Field | Before → after |
|---|---|---|
| 06-11-2026 | work[Amaravila - Ottasekharamangalam Road - Balance Work].paid_amount | 163743360 → 226321054 |
| 06-11-2026 | work[Amaravila - Ottasekharamangalam Road - Balance Work].approved_amount | 232133152 → 232126653 |
| 06-11-2026 | paid_amount | 284469554 → 347047248 |