PWD004-75-05 Parassala

Amaravila - Ottasekharamangalam Road - Balance Work

Spent on this package so far

₹10.55 crore

₹10,55,32,579

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Flags (1)

Overdue · Amaravila Ottasekharamanagalam road

Scheduled completion was 16-03-2026. That was 200 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Amaravila Ottasekharamanagalam road

In progress
38%Physical progress
29.3%Financial progress
Scheduled start16-09-2024
Scheduled completion16-03-2026
Contractor
Thajudeen A
Implementing agency (SPV)
KRFB
Contract amount
₹23,21,33,152₹23.21 crore
Amount paid
₹6,79,81,248₹6.8 crore
Paid to contractor
₹6,42,36,527₹6.42 crore
Administrative sanction (AS)
₹15,00,00,000₹15 crore
Financial sanction (FS)
₹35,81,50,861₹35.82 crore
Technical sanction (TS)
₹21,10,32,902₹21.1 crore
Tender amount
₹23,21,33,152₹23.21 crore
Current progress
80% work completed. DBM completed. Present work foreclosed on 19.5.2022. Balance work to be tendered. KWA estimate submitted to KIIFB. Work can be progressed further only after completion of LA. 11(1) published on 19.4.2022

Money trail

Estimated amount
₹35,81,50,861Estimate of sub-project PWD004-74, shared by 2 contract packages
Expenditure reported · this package
₹10,55,32,579
Expenditure reported · all 2 packages
₹21,77,56,90760.8% of the estimated amount

Details

Project code
PWD004-75-05
Department
Public Works
Constituency
ParassalaMLA: Shri C. K Hareendran

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Improvements to Amaravila - Ottasekharamangalam road by providing 50mm DBM & 30mm BC between Km 0/000 to 12/200”. The figures below are for that whole project, not this package alone.

Approved
₹35,81,50,861₹35.82 crore
Paid so far
₹28,44,69,55479.4% of the amount approved

This package

Work awarded
₹16.37 crorepaid
₹23.21 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org