Kanakkuമലയാളം
Public WorksApproved

Improvements to Jacobs road upto Challapally (Padimon Kottangal Chunkkappara Challapally road)

Approved by KIIFB

₹36.9 crore

₹36,90,00,000

Paid so far

₹34.68 crore

₹34,68,15,974 · 94% of the amount approved

Works

2

₹34.68 crore paid across the works

Works (2)

Improvements to Jacobs road upto Challapally (Padimon Kottangal Chunkkappara Challapally road - Shifting utilities by KSEB

Work awarded
₹34.25 lakhpaid
₹34.25 lakhapproved

Total of the works: ₹34,71,17,184 approved, ₹34,68,15,974 paid.

Details

Department
Public Works
Implementing agency (SPV)
Kerala Road Fund Board (KRFB)
Announced under
137 Roads
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
02-10-2026
First recorded
30-09-2026

The same project on the map dashboard

KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.