PWD004-62-01 Ranni

Improvements to Jacobs road - Contract work

Estimated amount

₹36.9 crore

₹36,90,00,000 · ₹32.62 crore spent

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: Contract Process Completed · How we group

Location

Flags (1)

Overdue · Jacobs Road upto Challapally

Scheduled completion was 30-11-2023. That was 1037 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Jacobs Road upto Challapally

In progress
100%Physical progress
99.9%Financial progress
Scheduled start10-10-2018
Scheduled completion30-11-2023
Implementing agency (SPV)
KRFB
Contract amount
₹34,36,91,822₹34.37 crore
Amount paid
₹34,33,90,612₹34.34 crore
Paid to contractor
₹31,76,84,516₹31.77 crore
Administrative sanction (AS)
₹15,00,00,000₹15 crore
Financial sanction (FS)
₹36,90,00,000₹36.9 crore
Technical sanction (TS)
₹34,76,45,159₹34.76 crore
Tender amount
₹34,38,88,303₹34.39 crore
Letter of acceptance (LOA)
₹34,38,88,303₹34.39 crore
Current progress
work completed.

Money trail

Estimated amount
₹36,90,00,000₹36.9 crore
Expenditure reported
₹32,62,32,33988.4% of the estimated amount

Details

Project code
PWD004-62-01
Department
Public Works
Constituency
Ranni

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Improvements to Jacobs road upto Challapally (Padimon Kottangal Chunkkappara Challapally road)”.

Approved
₹36,90,00,000₹36.9 crore
Paid so far
₹34,68,15,97494% of the amount approved

Source: KIIFB project status (kiifb.org). How we joined the two sources

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…