Public WorksApproved

Construction of Coastal Highway in Malappuram District Reach I - Padinjarekkara to Unniyal Junction Km 0/000 to 15/000

Approved by KIIFB

₹57.76 crore

₹57,75,97,101

Paid so far

₹32.53 crore

₹32,52,61,979 · 56.3% of the amount approved

Works

3

₹32.53 crore paid across the works

KIIFB's list gives “payment released” for this project as ₹97,57,85,937. That is exactly 3 times what the works below add up to; for projects filed under several districts the list counts the same payments more than once. So we show the total of the works: ₹32,52,61,979.

Works (3)

Construction of Coastal Highway in Malappuram District Reach I - Padinjarekkara to Unniyal Junction Km 0/000 to 15/000 - shifting utilities by KSEB

Work awarded
₹84.54 lakhpaid
₹1.06 croreapproved

Construction of Coastal Highway in Malappuram District Reach I - Padinjarekkara to Unniyal Junction Km 0/000 to 15/000 - LA

Work awarded
₹21.91 lakhpaid
₹2 croreapproved

Total of the works: ₹34,91,16,892 approved, ₹32,52,61,979 paid.

Details

Department
Public Works
Implementing agency (SPV)
Kerala Road Fund Board (KRFB)
Announced under
Coastal Highway
KIIFB status
Approved

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
02-10-2026
First recorded
30-09-2026

The same project on the map dashboard

KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.