Work 1
In progress100%Physical progress
93.4%Financial progress
Scheduled start08-03-2019
Scheduled completion16-08-2025
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹31,85,12,689₹31.85 crore
- Amount paid
- ₹29,74,68,422₹29.75 crore
- Paid to contractor
- ₹27,53,93,000₹27.54 crore
- Administrative sanction (AS)
- ₹65,00,00,00,000₹6,500 crore
- Financial sanction (FS)
- ₹57,75,97,101₹57.76 crore
- Technical sanction (TS)
- ₹1,95,68,467₹1.96 crore
- Tender amount
- ₹52,39,92,898₹52.4 crore
- Letter of acceptance (LOA)
- ₹52,39,92,898₹52.4 crore
- Current progress
- Work awarded to ULCCS and 45% completed. No provision for LA in original DPR, later Revised FS with a provision of 4.3Crores for LA in 4kms was accorded by KIIFB on 31.01.2022. Accordingly Form 2 - requisition form submitted. TOC expired on 07.11.2021