Coastal Highway in Malappuram District Reach I - Padinjarekkara to Unniyal Junction Km 0/000 to 15/000- Contract Work

Estimated amount

₹57.76 crore

₹57,75,97,101 · ₹29.9 crore spent

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Flags (1)

Overdue · #1

Scheduled completion was 16-08-2025. That was 412 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Work 1

In progress
100%Physical progress
93.4%Financial progress
Scheduled start08-03-2019
Scheduled completion16-08-2025
Implementing agency (SPV)
KRFB
Contract amount
₹31,85,12,689₹31.85 crore
Amount paid
₹29,74,68,422₹29.75 crore
Paid to contractor
₹27,53,93,000₹27.54 crore
Administrative sanction (AS)
₹65,00,00,00,000₹6,500 crore
Financial sanction (FS)
₹57,75,97,101₹57.76 crore
Technical sanction (TS)
₹1,95,68,467₹1.96 crore
Tender amount
₹52,39,92,898₹52.4 crore
Letter of acceptance (LOA)
₹52,39,92,898₹52.4 crore
Current progress
Work awarded to ULCCS and 45% completed. No provision for LA in original DPR, later Revised FS with a provision of 4.3Crores for LA in 4kms was accorded by KIIFB on 31.01.2022. Accordingly Form 2 - requisition form submitted. TOC expired on 07.11.2021

Money trail

Estimated amount
₹57,75,97,101₹57.76 crore
Expenditure reported
₹29,90,42,86651.8% of the estimated amount

Details

Project code
PWD014-01-01
Department
Public Works
Constituency
Tanur,Tirur,Thavanur

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Construction of Coastal Highway in Malappuram District Reach I - Padinjarekkara to Unniyal Junction Km 0/000 to 15/000”.

Approved
₹57,75,97,101₹57.76 crore
Paid so far
₹32,52,61,97956.3% of the amount approved

This package

Work awarded
₹31.46 crorepaid
₹31.85 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org