CIN001-07-01 Ernakulam

Construction of Tank Bund Road Bridge in Chilavannur Canal

Estimated amount

₹39.07 crore

₹39,06,64,651 · ₹13.98 crore spent

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: Contract Process Completed · How we group

Location

Flags (1)

Overdue · #1

Scheduled completion was 22-07-2025. That was 437 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 1 · Since 30-09-2026

Works (1)

Work 1

In progress
38%Physical progress
36.4%Financial progress
Scheduled start23-11-2023
Scheduled completion22-07-2025
Implementing agency (SPV)
KMRL
Contract amount
₹38,77,67,345₹38.78 crore
Amount paid
₹14,11,44,987₹14.11 crore
Paid to contractor
₹12,63,28,670₹12.63 crore
Administrative sanction (AS)
₹15,28,27,00,000₹1,528.27 crore
Financial sanction (FS)
₹39,06,64,651₹39.07 crore
Technical sanction (TS)
₹32,58,43,420₹32.58 crore
Tender amount
₹38,77,67,345₹38.78 crore

Money trail

Estimated amount
₹39,06,64,651₹39.07 crore
Expenditure reported
₹13,97,55,86735.8% of the estimated amount

Details

Project code
CIN001-07-01
Department
Coastal Shipping & Inland Navigation
Constituency
ErnakulamMLA: Shri T J Vinod
Name as KIIFB publishes it
CONSTRUCTION OF TANK BUND ROAD BRIDGE IN CHILAVANNUR CANAL

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Chilavannur Bund Road Bridge”.

Approved
₹39,06,64,651₹39.07 crore
Paid so far
₹18,40,43,84247.1% of the amount approved

This package

Work awarded
₹18.24 crorepaid
₹38.78 croreapproved

Source: KIIFB project status (kiifb.org). Checked 30-09-2026. How we joined the two sources

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026