Construction of 6 Watch Towers in Nilambur North, Nilambur South, Wayanad North and Wayanad South Forest Divisions
Estimated amount
Not published
No figure is published for this package alone.
Stage
- Preparation
- Technical sanction
- Tender
- Contract
- Work plan
KIIFB status: Design Basis Report Approved · How we group
Location
The location KIIFB records lies outside this map.
Money trail
- Estimated amount
- ₹5,02,18,090Estimate of sub-project FOR001-08, shared by 2 contract packages
- Expenditure reported · this package
- Not published
- Expenditure reported · all 2 packages
- Not published
Details
- Project code
- FOR001-08-01
- Department
- Forest & Wild Life
- Executing agency
- State Forest Development Agency Kerala
- Constituency
- ThiruvananthapuramMLA: Shri Antony Raju
What KIIFB approved and paid
On KIIFB's project status page this belongs to “Manual Surveillance: Construction of Watch Towers”. The figures below are for that whole project, not this package alone.
- Approved
- ₹5,02,18,090₹5.02 crore
- Paid so far
- ₹00% of the amount approved
Source: KIIFB project status (kiifb.org). Checked 30-09-2026. How we joined the two sources
What we don't know yet
The KIIFB dashboard does not publish these for this project:
- Contractor, contract amount, scheduled dates, payments and physical progress
- Expenditure so far
Source
- Source
- KIIFB integrated dashboardgis.kiifb.org
- Retrieved
- 30-09-2026
- First recorded
- 30-09-2026
- SHA-256
- 04a00101b9212117…