Approved and paid

From KIIFB's own project status page: what it approved for the projects listed under Thiruvananthapuram, and what has been paid. Some span several districts.

Project by project

Approved by KIIFB

₹19,933.91 crore

₹1,99,33,90,67,603

Paid so far

₹11,161.84 crore

56% of the amount approved

Projects and works

201

767 works · 28 projects still under evaluation

See them all

Who must repair it

For 287 finished PWD works, the contractor is still liable to repair defects. Which road or building, which contractor, and until when.

See the list

Flagged right now

Projects whose published figures crossed a threshold. A flag is not evidence of wrongdoing.

What the flags mean
  1. 137 RoadsPublic Works · Nedumangad₹1,185.19 croretotal of worksOverdue
  2. 182 RoadsPublic Works · Nedumangad₹169.96 croretotal of worksPayment ahead of progress
  3. Trivandrum / Kozhikode Light Metro ProjectPublic Works · Kazhakoottam₹168.68 croretotal of worksOverdue
  4. 137 RoadsPublic Works · Kattakkada,Kovalam₹162.46 croretotal of worksOverdue
  5. Improvement to Petta- Anayara-Oruvathilkotta Road - ContractPublic Works · Kazhakoottam₹160.55 croreestimateOverdueWork plan
  6. Trivandrum / Kozhikode Light Metro ProjectPublic Works · Vattiyoorkavu₹84.61 croretotal of worksPayment ahead of progress

All flagged projects

By department

All projects

By constituency

MLA names are as the KIIFB dashboard lists them.

Where projects stand

KIIFB's status labels, grouped by us into plain stages.

Most spent so far

Full list
  1. GIS Package 4 - Construction of GIS Substations at Ettumanoor and VizhinjamPower · Ettumanoor, Kovalam₹112.28 crorespent so farWork plan
  2. TRAN 11: WRD025-12 - Comprehensive Water supply scheme to Pulimath, Nagaroor and Karavaram panchayaths in Thiruvananthapuram District, Phase - I, Construction of 9m diameter well, 18 MLD WTP, CWGM, CWPM, OHSRs, transformers, pumps and allied items, and Road restorationWater Resources · Attingal₹87.96 croreestimateWork plan
  3. Construction of IT Building at Technocity - Sri Kubera Constructions Private LtdInformation Technology · Kazhakoottam₹62.93 crorespent so farContract
  4. Upgrading Kerala University into Centre of Excellence in Academics and Research:- Infrastructure works at Karyavattom University CampusHigher Education · Kazhakoottam₹58.58 croreestimateWork plan
  5. Improvements to Hill Highway Kallikkadu to Parassala (First Phase - Kudappanamood to Parassala Ch. Km 15/715 to 28/760 and Ch. 31/410 to 33/860) in Thiruvanathapuram District - Balance WorkPublic Works · Parassala₹48.07 crorespent so farWork plan

How to read this

You can see the source

Every figure comes from a government body's own page. We keep a dated copy of that page, and you can download it.

One rule for everyone

Flags come from published thresholds, applied the same way to every project, party and constituency.

We say what is missing

Each project page lists what the source does not publish, such as the contractor or the payments.