Kanakkuമലയാളം
FOR003-01-17 Aruvikkara

Upgradation of Road from Kavadimoola to Elephant Rehabilitation Centre, Kottoor.

Spent on this package so far

₹6.15 crore

₹6,15,24,533

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: Contract Process Completed · How we group

Location

Works (1)

Work 1

Completed
100%Physical progress
85.1%Financial progress
Scheduled start20-06-2023
Scheduled completion31-08-2025
Implementing agency (SPV)
NPFDA
Contract amount
₹6,42,66,062₹6.43 crore
Amount paid
₹5,46,70,113₹5.47 crore
Paid to contractor
₹5,13,66,689₹5.14 crore
Administrative sanction (AS)
₹1,05,00,00,000₹105 crore
Financial sanction (FS)
₹82,38,25,686₹82.38 crore
Technical sanction (TS)
₹6,42,66,062₹6.43 crore
Tender amount
₹5,69,55,136₹5.7 crore
Letter of acceptance (LOA)
₹5,69,55,136₹5.7 crore

Money trail

Estimated amount
₹82,38,25,686Estimate of sub-project FOR003-01, shared by 18 contract packages
Expenditure reported · this package
₹6,15,24,533
Expenditure reported · all 18 packages
₹65,74,67,21279.8% of the estimated amount

Details

Project code
FOR003-01-17
Department
Forest & Wild Life
Constituency
AruvikkaraMLA: Shri G. Steephen

What KIIFB approved and paid

On KIIFB's project status page this belongs to “State-of-the-Art Elephant Rehabilitation Centre, Kottoor Phase I”. The figures below are for that whole project, not this package alone.

Approved
₹82,38,25,686₹82.38 crore
Paid so far
₹72,73,85,38388.3% of the amount approved

This package

Work started
₹6.38 crorepaid
₹6.43 croreapproved

Source: KIIFB project status (kiifb.org). Checked 30-09-2026. How we joined the two sources

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project