Kanakkuമലയാളം
FOR004-02-02 Ollur

Construction of Compound Wall for Zoological Park, Thrissur

Estimated amount

Not published

No figure is published for this package alone.

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹2,08,57,72,890Estimate of sub-project FOR004-02, shared by 8 contract packages
Expenditure reported · this package
Not published
Expenditure reported · all 8 packages
₹6,78,50,0963.3% of the estimated amount

Details

Project code
FOR004-02-02
Department
Forest & Wild Life
Constituency
OllurMLA: Shri K. Rajan

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Puthur Zoological Park, Wildlife Conservation & Research Phase II”. The figures below are for that whole project, not this package alone.

Approved
₹2,08,57,72,890₹208.58 crore
Paid so far
₹23,84,82,70611.4% of the amount approved

Source: KIIFB project status (kiifb.org). How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress
  • Expenditure so far

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project