This package
Work started₹2.93 crorepaid
₹2.93 croreapproved
₹2.82 crore
₹2,81,50,464
KIIFB status: Contract Process Completed · How we group
On KIIFB's project status page this belongs to “Erosion Mitigation Measures”. The figures below are for that whole project, not this package alone.
Source: KIIFB project status (kiifb.org). Checked 01-10-2026. How we joined the two sources
The KIIFB dashboard does not publish these for this project: