Kerala · Kannur district
Where the public money goes
What was sanctioned, who got the contract, what has been paid and how far the work has come. Every number carries its source.
projects20 departments, 11 constituencies
₹1,403.55 crorespent so faras KIIFB reports it
18projects with a flaga flag is not an accusation
2 Octlast checkedagainst the KIIFB dashboard, daily
Approved and paid
From KIIFB's own project status page: what it approved for the projects listed under Kannur, and what has been paid. Some span several districts.
Approved by KIIFB
₹24,348.25 crore
₹2,43,48,25,03,918
Paid so far
₹7,718.73 crore
31.7% of the amount approved
Provisional: the work tables of 160 projects are still to be read.
Who must repair it
For 230 finished PWD works, the contractor is still liable to repair defects. Which road or building, which contractor, and until when.
Flagged right now
Projects whose published figures crossed a threshold. A flag is not evidence of wrongdoing.
- Hill HighwayPublic Works · Irikkur,Peravoor₹83.17 croretotal of works
- 182 RoadsPublic Works · Taliparamba₹69.53 croretotal of works
- Kuppam- Chudala -Panapuzha & Mathamangalam Eriyam Road- contract workPublic Works · Kalliasseri, Kalliasseri,Taliparamba, Taliparamba₹62.08 croreestimate
- 182 RoadsPublic Works · Taliparamba₹60.76 croretotal of works
- 182 RoadsPublic Works · Irikkur₹47.72 croretotal of works
- Kuthuparamba Ring Road in Kannur District-Contract workPublic Works · Kuthuparamba₹40.24 croreestimate
By department
All projectsBy constituency
MLA names are as the KIIFB dashboard lists them.
Where projects stand
KIIFB's status labels, grouped by us into plain stages.
Most spent so far
Full list- DEVELOPMENT OF MALABAR CANCER CENTRE, THALASSERY - PHASE I - Construction of new Radio Therapy Block, Renovation of Out-Patient Block and Site Development WorksHealth & Family Welfare · Thalassery₹98.2 croreestimate
- Education Hub at PinarayiHigher Education · Dharmadam₹71.13 crorespent so far
- WSS to Mattannur and Iritty Municipalities- Phase II-Package IWater Resources · Mattannur₹69.75 crorespent so far
- Comprehensive Development of Muzhuppilangad -Dharmadom Beach in Kannur District-Character Area-1Tourism · Dharmadam₹65.14 crorespent so far
- GIS IV - Contruction of 220kV GIS Substation at ThalasseryPower · Thalassery₹65.41 croreestimate
How to read this
You can see the source
Every figure comes from a government body's own page. We keep a dated copy of that page, and you can download it.
One rule for everyone
Flags come from published thresholds, applied the same way to every project, party and constituency.
We say what is missing
Each project page lists what the source does not publish, such as the contractor or the payments.