Kanakkuമലയാളം
FSH002-10-01 Kalliasseri

Gghss, Madayi, Kannur - Civil Works

Spent on this package so far

₹1.49 crore

₹1,48,68,098

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹6,26,79,660Estimate of sub-project FSH002-10, shared by 13 contract packages
Expenditure reported · this package
₹1,48,68,098
Expenditure reported · all 13 packages
₹4,83,69,23577.2% of the estimated amount

Details

Project code
FSH002-10-01
Department
Fisheries
Constituency
KalliasseriMLA: Shri M. Vijin
Name as KIIFB publishes it
GGHSS, MADAYI, KANNUR - Civil Works

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Educational Infrastructure Works at Kannur District Phase-2”. The figures below are for that whole project, not this package alone.

Approved
₹6,26,79,660₹6.27 crore
Paid so far
₹5,13,47,22881.9% of the amount approved

This package

Work awarded
₹1.58 crorepaid
₹1.58 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project