Kanakkuമലയാളം

Estimated amount

Not published

No figure is published for this package alone.

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: Tender Completed · How we group

Location

Money trail

Estimated amount
₹12,65,68,930Estimate of sub-project GED003-05, shared by 12 contract packages
Expenditure reported · this package
Not published
Expenditure reported · all 12 packages
₹6,72,47,45453.1% of the estimated amount

Details

Project code
GED003-05-11
Department
General Education
Constituency
PuthukkadMLA: Shri K.K. Ramachandran

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Thrissur - Cluster 10”. The figures below are for that whole project, not this package alone.

Approved
₹12,65,68,930₹12.66 crore
Paid so far
₹7,87,39,61062.2% of the amount approved

This package

Work started
₹46.48 lakhpaid
₹1.28 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress
  • Expenditure so far

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project