GED003-06-03 Chadayamangalam

Construction of school building to GOVT.UPS Nilamel in Nilamel GP, Kollam

Spent on this package so far

₹75.09 lakh

₹75,08,909

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹16,06,61,345Estimate of sub-project GED003-06, shared by 17 contract packages
Expenditure reported · this package
₹75,08,909
Expenditure reported · all 17 packages
₹9,61,31,50959.8% of the estimated amount

Details

Project code
GED003-06-03
Department
General Education
Constituency
ChadayamangalamMLA: Smt J. Chinjurani

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Kollam - Cluster 4”. The figures below are for that whole project, not this package alone.

Approved
₹16,06,61,345₹16.07 crore
Paid so far
₹10,66,45,81766.4% of the amount approved

This package

Work awarded
₹78.41 lakhpaid
₹1.06 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…