Spent on this package so far

₹1.04 crore

₹1,03,54,233

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹11,71,49,265Estimate of sub-project GED003-18, shared by 10 contract packages
Expenditure reported · this package
₹1,03,54,233
Expenditure reported · all 10 packages
₹7,73,73,72066% of the estimated amount

Details

Project code
GED003-18-04
Department
General Education
Constituency
ThalasseryMLA: Shri A. N. Shamseer

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Kannur Cluster - 18”. The figures below are for that whole project, not this package alone.

Approved
₹11,71,49,265₹11.71 crore
Paid so far
₹8,64,95,16473.8% of the amount approved

This package

Work awarded
₹1.09 crorepaid
₹1.1 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…