GED003-27-04 Irikkur

Project- Infrastructure Development of School GHSS Nedungome in Sreekandapuram Municipality Kannur

Spent on this package so far

₹86.83 lakh

₹86,83,429

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹13,14,02,581Estimate of sub-project GED003-27, shared by 12 contract packages
Expenditure reported · this package
₹86,83,429
Expenditure reported · all 12 packages
₹6,44,51,34949% of the estimated amount

Details

Project code
GED003-27-04
Department
General Education
Constituency
IrikkurMLA: Shri Sajeev Joseph
Name as KIIFB publishes it
KILA-KIIFB- PROJECT- INFRASTRUCTURE DEVELOPMENT OF SCHOOL GHSS Nedungome IN SREEKANDAPURAM MUNICIPALITY KANNUR

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Malappuram, Kozhikode and Kannur - Cluster 27”. The figures below are for that whole project, not this package alone.

Approved
₹13,14,02,581₹13.14 crore
Paid so far
₹7,43,04,21856.5% of the amount approved

This package

Work awarded
₹89.96 lakhpaid
₹94.22 lakhapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…