GED005-10-04 Kunnamangalam

Chathamangalam R. E. C. Govt. HSS

Spent on this package so far

₹4.05 crore

₹4,05,24,852

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹25,00,00,000Estimate of sub-project GED005-10, shared by 5 contract packages
Expenditure reported · this package
₹4,05,24,852
Expenditure reported · all 5 packages
₹18,95,20,25675.8% of the estimated amount

Details

Project code
GED005-10-04
Department
General Education
Constituency
KunnamangalamMLA: Shri P. T. A. Rahim
Name as KIIFB publishes it
CHATHAMANGALAM R. E. C. GOVT. HSS

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026