Kanakkuമലയാളം

Spent on this package so far

₹3.58 crore

₹3,57,63,966

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹44,84,87,000Estimate of sub-project GED005-17, shared by 10 contract packages
Expenditure reported · this package
₹3,57,63,966
Expenditure reported · all 10 packages
₹34,02,59,23375.9% of the estimated amount

Details

Project code
GED005-17-09
Department
General Education
Constituency
ParavurMLA: Shri V. D. Satheesan
Constituency
AngamalyMLA: Shri Roji M. John

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project