Spent on this package so far

₹37.38 lakh

₹37,38,048

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: Contract Process Completed · How we group

Location

Money trail

Estimated amount
₹49,93,68,000Estimate of sub-project GED005-20, shared by 13 contract packages
Expenditure reported · this package
₹37,38,048
Expenditure reported · all 13 packages
₹39,84,20,12479.8% of the estimated amount

Details

Project code
GED005-20-07
Department
General Education
Constituency
MalappuramMLA: Shri P. Ubaidulla
Name as KIIFB publishes it
GOVT GHSS MALAPPURAM

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Malappuram Cluster Phase 2”. The figures below are for that whole project, not this package alone.

Approved
₹49,93,68,000₹49.94 crore
Paid so far
₹41,60,23,00183.3% of the amount approved

This package

Work started
₹39.17 lakhpaid
₹89.61 lakhapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project