GHSS KUTHUPARAMBU
Estimated amount
Not published
No figure is published for this package alone.
Stage
- Preparation
- Technical sanction
- Tender
- Contract
- Work plan
KIIFB status: Contract Process Completed · How we group
Money trail
- Estimated amount
- ₹23,33,97,170Estimate of sub-project GED006-04, shared by 7 contract packages
- Expenditure reported · this package
- Not published
- Expenditure reported · all 7 packages
- ₹7,67,65,00332.9% of the estimated amount
Details
- Project code
- GED006-04-03
- Department
- General Education
- Executing agency
- Kerala Institute of Local Administration (KILA)
- Constituency
- KuthuparambaMLA: Shri K.P. Mohanan
What KIIFB approved and paid
On KIIFB's project status page this belongs to “Kannur Cluster 1”. The figures below are for that whole project, not this package alone.
- Approved
- ₹23,33,97,170₹23.34 crore
- Paid so far
- ₹63,21,03,192₹63.21 crore
Source: KIIFB project status (kiifb.org). How we joined the two sources
What we don't know yet
The KIIFB dashboard does not publish these for this project:
- Contractor, contract amount, scheduled dates, payments and physical progress
- Expenditure so far
Source
- Source
- KIIFB integrated dashboardgis.kiifb.org
- Retrieved
- 30-09-2026
- First recorded
- 30-09-2026
- SHA-256
- 04a00101b9212117…
Other packages under the same sub-project
- Govt. VHSS Edayanoor ₹3.09 crore spent
- CHMKSGHSS Matool ₹2.82 crore spent
- IMNSGHSS Mayyil ₹1.77 crore spent
- Kpr Gopala Smaraka GHSS Kalyasseri Not published
- GBHSS Cherukunnu Not published
- GHSS Kuthuparambu Not published