GVHSS Madapally, Kozhikode
Spent on this package so far
₹2.79 crore
₹2,78,72,569
Stage
- Preparation
- Technical sanction
- Tender
- Contract
- Work plan
KIIFB status: Contract Process Completed · How we group
Money trail
- Estimated amount
- ₹11,16,00,000Estimate of sub-project GED008-26, shared by 4 contract packages
- Expenditure reported · this package
- ₹2,78,72,569
- Expenditure reported · all 4 packages
- ₹10,24,03,01391.8% of the estimated amount
Details
- Project code
- GED008-26-03
- Department
- General Education
- Executing agency
- WAPCOS Limited
- Constituency
- Vatakara
What KIIFB approved and paid
On KIIFB's project status page this belongs to “Kozhikode Phase-3 Cluster 3”. The figures below are for that whole project, not this package alone.
- Approved
- ₹11,16,00,000₹11.16 crore
- Paid so far
- ₹42,85,83,584₹42.86 crore
Source: KIIFB project status (kiifb.org). How we joined the two sources
What we don't know yet
The KIIFB dashboard does not publish these for this project:
- Contractor, contract amount, scheduled dates, payments and physical progress
Source
- Source
- KIIFB integrated dashboardgis.kiifb.org
- Retrieved
- 30-09-2026
- First recorded
- 30-09-2026
- SHA-256
- 04a00101b9212117…
Other packages under the same sub-project
- Madapally GGHSS, Kozhikode ₹2.85 crore spent
- G.H.S.S Kallachi ₹2.56 crore spent
- Cheruvadi Government H.S.S, Kozhikode ₹2.04 crore spent