GHSS Thonnakkal
Spent on this package so far
₹2.76 crore
₹2,75,69,912
Stage
- Preparation
- Technical sanction
- Tender
- Contract
- Work plan
KIIFB status: WBS Base One Approved · How we group
Money trail
- Estimated amount
- ₹6,00,00,000Estimate of sub-project GED008-34, shared by 2 contract packages
- Expenditure reported · this package
- ₹2,75,69,912
- Expenditure reported · all 2 packages
- ₹5,19,88,70186.6% of the estimated amount
Details
- Project code
- GED008-34-02
- Department
- General Education
- Executing agency
- INKEL Limited
- Constituency
- ChirayinkeezhuMLA: Shri V. Sasi
What we don't know yet
The KIIFB dashboard does not publish these for this project:
- Contractor, contract amount, scheduled dates, payments and physical progress
Source
- Source
- KIIFB integrated dashboardgis.kiifb.org
- Retrieved
- 30-09-2026
- First recorded
- 30-09-2026
- SHA-256
- 04a00101b9212117…
Other packages under the same sub-project
- GHSS Kilimanoor ₹2.44 crore spent