Estimated amount
Not published
No figure is published for this package alone.
Stage
- Preparation
- Technical sanction
- Tender
- Contract
- Work plan
KIIFB status: Technical Sanction Created · How we group
Location
The location KIIFB records lies outside this map.
Money trail
- Estimated amount
- ₹12,00,00,000Estimate of sub-project GED008-39, shared by 7 contract packages
- Expenditure reported · this package
- Not published
- Expenditure reported · all 7 packages
- ₹8,18,66,42168.2% of the estimated amount
Details
- Project code
- GED008-39-02
- Department
- General Education
- Executing agency
- Kerala Infrastructure and Technology for Education (KITE)
- Constituency
- VarkalaMLA: Shri V. Joy
What we don't know yet
The KIIFB dashboard does not publish these for this project:
- Contractor, contract amount, scheduled dates, payments and physical progress
- Expenditure so far
Source
- Source
- KIIFB integrated dashboardgis.kiifb.org
- Retrieved
- 30-09-2026
- First recorded
- 30-09-2026
- SHA-256
- 04a00101b9212117…
Other packages under the same sub-project
- SMGHS, Kunnamthanam ₹3.19 crore spent
- GHSS, Panamattam ₹2.13 crore spent
- SBVGHSS, Panmanamalayil ₹2.03 crore spent
- GHSS, Chittar ₹83.58 lakh spent
- Diet School (B.t.s) Attingal Not published
- GVHSS, Kulathur Not published