CPNS GHSS, Mathamangalam
Estimated amount
Not published
No figure is published for this package alone.
Stage
- Preparation
- Technical sanction
- Tender
- Contract
- Work plan
KIIFB status: Project Initiated · How we group
Money trail
- Estimated amount
- ₹6,35,30,000Estimate of sub-project GED008-46, shared by 6 contract packages
- Expenditure reported · this package
- Not published
- Expenditure reported · all 6 packages
- ₹7,29,34,360114.8% of the estimated amount
Details
- Project code
- GED008-46-01
- Department
- General Education
- Executing agency
- Kerala Infrastructure and Technology for Education (KITE)
- Constituency
- PayyannurMLA: Shri T.I. Madhusoodanan
What KIIFB approved and paid
On KIIFB's project status page this belongs to “Additional fund sanctioned by KIIFB for GHSS Munderi”. The figures below are for that whole project, not this package alone.
- Approved
- ₹6,35,30,000₹6.35 crore
- Paid so far
- ₹7,62,34,495₹7.62 crore
Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources
What we don't know yet
The KIIFB dashboard does not publish these for this project:
- Contractor, contract amount, scheduled dates, payments and physical progress
- Expenditure so far
Source
- Source
- KIIFB integrated dashboardgis.kiifb.org
- Retrieved
- 30-09-2026
- First recorded
- 30-09-2026
- SHA-256
- 04a00101b9212117…
Other packages under the same sub-project
- GHSS Kannadiparambu ₹4.1 crore spent
- G H S S Munderi ₹3.19 crore spent
- GHSS, Chavassery Not published
- VHSS Tagore Vidya Nikethan Not published
- GGVHSS, Cherukunnu Not published