Kanakkuമലയാളം

Spent on this package so far

₹2.79 crore

₹2,78,78,771

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹18,00,00,000Estimate of sub-project GED008-47, shared by 6 contract packages
Expenditure reported · this package
₹2,78,78,771
Expenditure reported · all 6 packages
₹18,27,52,720101.5% of the estimated amount

Details

Project code
GED008-47-06
Department
General Education
Executing agency
WAPCOS Limited
Constituency
BalusseriMLA: Shri K.M. Sachindev

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project