Kanakkuമലയാളം

Estimated amount

Not published

No figure is published for this package alone.

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: Technical Sanction Created · How we group

Location

Money trail

Estimated amount
₹8,79,00,000Estimate of sub-project GED008-59, shared by 5 contract packages
Expenditure reported · this package
Not published
Expenditure reported · all 5 packages
₹7,74,95,43488.2% of the estimated amount

Details

Project code
GED008-59-05
Department
General Education
Constituency
AttingalMLA: Smt. O. S. Ambika

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Thiruvananthapuram Phase-3 Cluster 1”. The figures below are for that whole project, not this package alone.

Approved
₹8,79,00,000₹8.79 crore
Paid so far
₹8,10,21,03992.2% of the amount approved

Source: KIIFB project status (kiifb.org). Checked 01-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress
  • Expenditure so far

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…