Augmentation of Infrastructural Facilities at CKG Memorial Government College, Perambra, Kozhikode
Spent on this package so far
₹7.79 crore
₹7,79,32,983
Stage
- Preparation
- Technical sanction
- Tender
- Contract
- Work plan
KIIFB status: WBS Base One Approved · How we group
Money trail
- Estimated amount
- ₹14,87,68,310Estimate of sub-project HED007-20, shared by 2 contract packages
- Expenditure reported · this package
- ₹7,79,32,983
- Expenditure reported · all 2 packages
- ₹10,24,85,98868.9% of the estimated amount
Details
- Project code
- HED007-20-01
- Department
- Higher Education
- Executing agency
- KITCO Ltd
- Constituency
- PerambraMLA: Shri T. P. Ramakrishnan
What KIIFB approved and paid
On KIIFB's project status page this belongs to “Kozhikode Cluster Phase-3”. The figures below are for that whole project, not this package alone.
- Approved
- ₹14,87,68,310₹14.88 crore
- Paid so far
- ₹23,51,65,539₹23.52 crore
Source: KIIFB project status (kiifb.org). How we joined the two sources
What we don't know yet
The KIIFB dashboard does not publish these for this project:
- Contractor, contract amount, scheduled dates, payments and physical progress
Source
- Source
- KIIFB integrated dashboardgis.kiifb.org
- Retrieved
- 30-09-2026
- First recorded
- 30-09-2026
- SHA-256
- 04a00101b9212117…